Acceptable per NEC Art. 300.4 (D)?

Poll created by stevedangerfield on Apr 12, 2018

Cable stapled to side, and runs the length of a stud, within 1/2" of front/nailing surface of stud.Cable staple to side, and routed full length of stud within ~3/4" of stud nailing surface.

2 total votes You cannot vote on this poll
  • Pictures depict an acceptable installation.
    0
  • Pictures depict an unacceptable installation. Cable must be moved or nailing plates must be installed on stud nailing surface wherever cable is within 1-1/4" of nailing surface.
    1
  • Pictures depict an unacceptable installation. Cable must be moved or physical protection/barrier must be installed to protect from angled or direct nail or screw penetration wherever cable is within 1-1/4" of nailing surface.