Is it necessary to bond down conductors at the top and bottom of a structural steel column even if inside pvc conduit?

Question asked by Ferdinand Ramos on Sep 2, 2017
Latest reply on Sep 7, 2017 by chriscarlson

I'm installing a LPS on a steel frame building.  I have some down conductors that go directly from the roof to the ground rod through PVC pipe, others exit the PVC pipe and terminate on a 'through wall' connection b/c the grade outside is higher than the inside floor.  